AI Infra Atlas

Methodology and assumptions

How to read this model.

This atlas represents a simplified but physically coherent data-center architecture. It is an educational model with representative configurations; it is not a blueprint for any specific facility and does not describe any operator's actual design.

Who this is for

Curious non-specialists first: investors, policymakers, journalists, students and people working in tech who want to understand what an AI data center physically is. Engineers (electrical, mechanical, civil, network) are a second audience: they should find the system logic, vocabulary and orders of magnitude right, and can open Pro mode for full specs. It is not a design, sizing or permitting tool.

How accurate are the numbers?

Kind of numberExampleExpect it to be
Vendor specBlackwell transistors, NVL72 GPU countExact as published
ReportedQueue size, deal sizes, capex rangesRight within ≈10–30%; dated, will change
TypicalPipe sizes, voltages, rack kW, floor loadsA real range used in practice; any given site may sit outside it
EstimateLive electrons, water and signal rates, calculatorPhysics-based, order-of-magnitude right (≈±25–50%)
Illustrative3D layout, campus scale, equipment countsLogically correct, not to scale, not a real site

Rule of thumb: trust the direction and the order of magnitude everywhere, trust exact figures only where they are tagged as a vendor spec, and check dated items (deals, queues, prices) against the source before quoting them.

What is real and what is illustrative

Every one of the 91 components carries specifications labeled representative (a reasonable value for the class), illustrative (a teaching value), typical (common practice) or varies. Ranges are preferred to single numbers. Vendor figures for the Blackwell generation are vendor-published or widely reported. Supplier lists are categories, not endorsements, and supply-chain regions are representative geographies, not supplier claims.

The 3D campus is not to scale. Equipment is enlarged so it reads at campus distance, and roughly one world unit stands for two meters. Placement follows real logic: power enters from the transmission side and steps down toward the halls; fiber enters from the opposite side through diverse routes; heat rejection sits downwind of the halls; water treatment sits beside the cooling plant. Flows are drawn as Manhattan routes between the components they connect, so moving equipment in the data moves its flows.

Fact-check status

Every headline figure carries a status: a vendor specification, a value reported by a named source, an estimate made by this model, or a historical record.

Fact-check status of key figures
ClaimValueStatusSource
B200 transistors / process208B, TSMC 4NP, two diesVendor specNVIDIA Blackwell architecture materials
NVLink 5 bandwidth1.8 TB/s per GPU; 72-GPU domain in NVL72Vendor specNVIDIA
B200 / GB200 HBMUp to 192 GB HBM3e, ≈8 TB/sVendor specNVIDIA
GB200 NVL72 rack power≈120–132 kWReportedPotter (IFP, 2024); industry reporting
Rack kW by GPU generationHopper ≈40–60 kW; Blackwell ≈130–250 kWReportedCrucible Capital Part 2 (2025)
Air-cooling practical limit≈20–30 kW/rack (≈50 kW with RDHx)ReportedPotter (2024); Crucible Part 2
Average PUE trend≈2.5 (2007) to ≈1.5; hyperscale ≈1.1ReportedUptime Institute via Potter (2024)
Global data-center electricity≈1–1.3% of world electricity (2022)ReportedIEA via Potter (2024)
Large transformer lead time≈50–100+ weeksReportedCrucible Capital Part I (2025)
Grid interconnect, >75 MW≈2–5 yearsReportedCrucible Capital Part I (2025)
Uptime tier availability99.671% to 99.995%ReportedUptime Institute (public tier descriptions)
Gas plant capex≈$720–1,680/kWReportedEIA via Crucible Part I
SMR capex (early units)≈$4,000–6,000/kW, estimatedReportedCrucible Part I; industry estimates
Pod thermal behaviorThrottle ≈87 °C, shutdown ≈100 °CModel estimateThis atlas (teaching parameters)
WUE by cooling method0.15–1.8 L/kWhModel estimateThis atlas (illustrative central values)
All-in kW per GPU≈1.4–2.0 kWModel estimateDerived from reported rack power ÷ GPUs
Facility / IT capex per MW≈$12M / ≈$40MModel estimateIllustrative; IT figure as reported by Crucible Part 2
1961 microwave tower sabotage, UtahThree relay towers dynamitedHistoricalHu, A Prehistory of the Cloud (2015)

The scenario model

The live pod model

The operations view runs a small energy balance for one rack-scale system and multiplies by 16 racks. Heat into the liquid loop is 90% of rack power; coolant leaves at supply + Q ÷ (ṁ · cp), with 100 L/min at 30 °C supply (45 °C in warm-water mode). GPUs sit a thermal resistance above the coolant, throttle near 87 °C and shut down near 100 °C. Training is modeled as synchronous compute-then-communicate swings; inference as bursty demand. These are teaching parameters, not vendor data.

Redundancy tiers

Uptime Institute tier summary
Tier ITier IITier IIITier IV
Availability target99.671%99.741%99.982%99.995%
Power paths111 active + 1 alternate2 active
Component redundancyNN+1N+12N (fault tolerant)
Concurrently maintainableNoNoYesYes
Generator fuel on site (common practice)≈8 h≈24 h≈72 h≈96 h

Summarized from public descriptions of the Uptime Institute tiers and common design guides. Certification requires Uptime's own review.

Language rules

The atlas avoids claiming that every AI cluster uses one network technology, that all hyperscalers or neoclouds share a cooling topology, or that illustrative megawatt, density, water or cost figures are audited data. Cloud, hyperscaler and neocloud are useful categories, not fixed or mutually exclusive ones.

Accessibility and performance

Everything in the 3D view is also available as semantic HTML: the inspector, the text map, comparison tables and glossary. Flows pair every color with a distinct particle shape and line pattern. Reduced-motion and high-contrast modes are in the display settings. Rendering uses instancing for racks, tiles and particles, three quality tiers, adaptive resolution, and a text fallback when WebGL is unavailable.

Sources

Public vendor documentation for accelerator specifications; Uptime Institute and IEA public material for tiers and global energy context; and the reading list on the Field notes page (Crucible Capital's Datacenter Series, Brian Potter's essay for the Institute for Progress, and Tung-Hui Hu's A Prehistory of the Cloud). Source placeholders on each component are structured for future citations.